Schedule
The current approximate schedule for the procurement process is shown below. UPPCO reserves the right to extend or otherwise modify any portion of this schedule at any time or terminate the procurement process at any time at its sole discretion without compensation to any parties.
Step | Timetable |
---|---|
RFQ Stage | |
RFQ Issuance | 5:00 pm ET, August 03, 2020 |
Notice of Intent (NOI) Due | 5:00 pm ET, August 24, 2020 |
SOQs Due | 5:00 pm ET, August 28, 2020 |
Notification of Results of RFQ stage | 5:00 pm ET, September 15, 2020 |
RFP Stage | |
RFP Issuance | To Be Determined |
Tentative Proposal Due Date | Quarter 4, 2020 |
Developer Selection and Start of Contract Negotiations | Quarter 4, 2020/Quarter 1, 2021 |